MODELLING BUILDING CONSTRUCTION DURATIONS IN NIGERIA

 

Table Of Contents


  • Cover page Title page Certification Dedication Acknowledgement Abstract Organization of the work Table of Content

Project Abstract

Following widespread acceptance by researchers that the effects of qualitative/managerial construction time-influencing factors need to be considered in project scope-based construction time predicting models, several multivariate models combining project scope and qualitative/managerial factors have been developed. However, it has been shown in literature that the applicability of these models is clearly limited to the regions/countries where they were developed. This study was therefore aimed at developing a multivariate construction time predicting model that will be applicable to the Nigeria construction industry. A self-administered questionnaire survey was used to source information on the quantitative (project scope) factors considered in the study as well as to assess the extent of influence of the qualitative factors on construction time. Principal component regression was used for the data analysis and model development, using SPSS 16.0 for windows. Following a non-normal distribution of errors and a low R2 value obtained when multiple linear regression analysis was first conducted, the study’s data set was double log transformed and then partitioned/reclassified to account for public and private sector projects. Three models were developed following the multiple linear regression analysis repeated after transforming and partitioning/reclassifying the study’s data set. Two of these models (the public sector model and the private sector model) had high R2 values and were found after testing and validation, to be suitable for predicting construction time, while one of the models (the all projects model) had a low R2 value and was consequently found to be unsuitable for predicting construction time. The models with high R2 values serve as a usefultool to project managers and contractors for predicting construction time, thereby facilitating effective planning.

Project Overview

INTRODUCTION
1.1 Background to the study
The importance of ensuring accuracy and reliability of construction time estimates at the tendering stage cannot be overemphasized. Accurate early estimates of construction time typically provides clients and contractors with a basis for evaluating the success of a project and the efficiency of the project organisation (Nkado, 1995). They also provide them with a basis for ascertaining logistical and cash flow implications for feasibility, budgeting, planning, monitoring and even litigation purposes (Skitmore and Ng, 2003). Furthermore, they serve as a criteria in determining the best combination when performing time-cost optimization (Que, 2002). It is therefore clear that construction time has become a vital tool used by clients and contractors to ensure the success of construction projects. This success will however, only be achieved when construction time is accurately predicted.
Construction time/periods are often calculated on the basis of the planner’s own previous experience on similar projects (Choudhury and Phatak, 2004). However, as pointed out by Skitmore and Ng (2003), the need to reduce the problem of subjectivity associated with the planner’s experience and judgement to correctly interpret project and site information and make the best possible decisions, has long resulted in the development of construction time predicting models.
The development of construction time predicting models commenced with the use of project scope factors. Project scope is a measure of project size, which can be described as construction cost, project duration, gross floor area, number of storey, building type and procurement method (Walker, 1995).


Blazingprojects Mobile App

📚 Over 50,000 Project Materials
📱 100% Offline: No internet needed
📝 Over 98 Departments
🔍 Software coding and Machine construction
🎓 Postgraduate/Undergraduate Research works
📥 Instant Whatsapp/Email Delivery

Blazingprojects App

Related Research

Quantity Surveying. 4 min read

Development of a Sustainable Cost Estimation Model for Green Building Projects...

This project is about creating a simple and reliable way to estimate the costs involved in building green (or environmentally friendly) buildings. Green buildin...

BP
Blazingprojects
Read more →
Quantity Surveying. 3 min read

Digital Building Cost Estimation and Management System using AI and BIM Integration...

This project focuses on creating a computer-based system that helps estimate and manage the costs of building construction projects more accurately and efficien...

BP
Blazingprojects
Read more →
Quantity Surveying. 4 min read

Implementation of Building Information Modeling (BIM) in Quantity Surveying Practice...

The implementation of Building Information Modeling (BIM) in Quantity Surveying practice represents a significant advancement in the construction industry that ...

BP
Blazingprojects
Read more →
Quantity Surveying. 2 min read

Implementation of Building Information Modeling (BIM) in Quantity Surveying Practice...

The implementation of Building Information Modeling (BIM) in Quantity Surveying Practices for Cost Estimation and Risk Management represents a pivotal advanceme...

BP
Blazingprojects
Read more →
Quantity Surveying. 4 min read

Analysis of Building Information Modelling (BIM) Implementation in Quantity Surveyin...

The project on "Analysis of Building Information Modelling (BIM) Implementation in Quantity Surveying Practice" aims to explore the integration of Bui...

BP
Blazingprojects
Read more →
Quantity Surveying. 3 min read

Utilization of Building Information Modeling (BIM) in Cost Estimation and Value Engi...

The utilization of Building Information Modeling (BIM) in cost estimation and value engineering for construction projects is a critical aspect of modern constru...

BP
Blazingprojects
Read more →
Quantity Surveying. 4 min read

Optimizing Cost Estimation Techniques in Construction Projects: A Case Study...

The research project titled "Optimizing Cost Estimation Techniques in Construction Projects: A Case Study" aims to investigate and improve the methods...

BP
Blazingprojects
Read more →
Quantity Surveying. 4 min read

Implementation of Building Information Modeling (BIM) in Quantity Surveying Practice...

The project topic "Implementation of Building Information Modeling (BIM) in Quantity Surveying Practice: A Case Study Approach" focuses on the integra...

BP
Blazingprojects
Read more →
Quantity Surveying. 2 min read

Digital Transformation in Quantity Surveying: Evaluating the Impact of Building Info...

Digital Transformation in Quantity Surveying: Evaluating the Impact of Building Information Modeling (BIM) on Cost Estimation and Analysis Overview: The const...

BP
Blazingprojects
Read more →
WhatsApp Click here to chat with us