Design And Installation Of 200 Watt Solar Power System
Table Of Contents
- Title Page Approval pageDedication Acknowledgement AbstractTable of contentList of figuresList of tablesCHAPTER ONE:
- 1.0INTRODUCTION1.1 Need for the project1.2 Scope of study1.3 Definition of termsCHAPTER TWO:
- 2.0LITERATURE REVIEW2.1 The basics of solar power system2.2 Principle of solar panel2.
- 2.1Estimating system out2.
- 2.2Standard test conditions2.
- 2.3Temperature2.
- 2.4Dirt and dust2.
- 2.5Mismatch and wiring losses2.3 Solar charge controller2.4 Principle of inverter2.
- 4.1Inverter sizing2.
- 4.2DC to AC conversion losses2.5 solar battery2.
- 5.1Temperature effect2.
- 5.2Battery voltage2.
- 5.3Battery power conversion efficiency2.
- 5.4Monitoring and maintenanceCHAPTER THREE:
- 3.0SYSTEM OPERATION3.1 Block diagram of the system3.2 System operation with block diagramCHAPTER FOUR:
- 4.0SYSTEM DESIGN4.1 Load evaluation and power consumption table4.
- 1.1Calculating power consumption4.2 Battery sizing4.3 Solar panel sizing4.
- 3.1Typical Pv electrical system types4.
- 3.2Solar array sizing worksheetCHAPTER FIVE:
- 5.0PROCUREMENT AND INSTALLATION5.1 Procurement5.2 Determination of installation site5.
- 2.1Mounting options5.3 Installation procedureCHAPTER SIX:
- 6.0TEST AND RESULT6.1 Test and resultsCHAPTER SEVEN:
- 7.0CONCLUSION AND RECOMMENDATION7.1 Conclusion7.2 Recommendation7.3 LimitationReference
Project Abstract
The 200W solar system was determined by load assessment, solar panel number determination, battery requirement and then inverter sizing. A complete solar panel rated at 200w was however purchased, together with 2 no. 150A solar battery, 1500W inverter and also 10A charge controller. These were assembled together with necessary protective gadgets like cut out switches; to give the 200W expected. The solar panel was mounted outside the building to allow for maximum collection of sun energy. It is expected that the system will help the department meet up with its office duties even when central power is not available.
Project Overview
INTRODUCTION
1.1 NEED FOR THE PROJECT
The general objective of the system is to provide efficiency, steadiness in the use of power appliances, by ensuring continuous availability of power supply even in the absence of mains. Uninterruptability of the system made it possible to eliminate all suspense from mains outage during the execution of an important and urgent assignment as may be required.
For better production of the system, the system was operated at a fully charged condition of the battery.
The project was rated 200W of 220V and 50Hz. It was expected that at this condition, it was favourable to carry load of the stipulated power. Loads of low power factors are not helpful since they produce spikes. Overloading is not potent to provide zero change over time and the inverter had LEDs which indicates mains failure and battery discharge and system fault.1.2 SCOPE OF STUDY
This solar power source makes it possible to provide a clean reliable supply of alternative electricity free of sags or surges which could be found in the line voltage frequency.
The solar power system (SPS) system achieved this by direct current from solar panel and by rectifying the standard main supply, using the direct current to charge the batteries and to provide clean alternative power by passing the energy a filter system.
It has zero change over time and LEDs which indicates mains fail and battery discharge level and it provides 100% protection against line noise, spikes surges and audio frequency interference.1.3 DEFINITION OF TERMS
1. Inverter unit: This unit converts a DC voltage into AC voltage with the help of the inverter unit.
2. Automatic Control Unit: This provides all the required control needed to meet up the objective of the whole system
3. Battery Unit: This is a secondary cell unit, capable of storing enough DC voltage from either sun or AC main, of which is later converted to AC voltage.