ANALYTICAL AND APPROXIMATE VARIANCE OF PUBLIC BUILDING TOTAL PROJECT COST, ESTIMATION BY MEAN COMPONENT COSTS METHOD

 

Table Of Contents


Chapter ONE

INTRODUCTION

  • 1.1Introduction
  • 1.2Background of Study
  • 1.3Problem Statement
  • 1.4Objective of Study
  • 1.5Limitation of Study
  • 1.6Scope of Study
  • 1.7Significance of Study
  • 1.8Structure of the Research
  • 1.9Definition of Terms

Chapter TWO

LITERATURE REVIEW

  • 2.1Overview of Cost Estimation Methods
  • 2.2Mean Component Costs Method in Project Cost Estimation
  • 2.3Advantages of Using Mean Component Costs Method
  • 2.4Disadvantages of Using Mean Component Costs Method
  • 2.5Comparison with Other Cost Estimation Methods
  • 2.6Case Studies on Mean Component Costs Method
  • 2.7Critiques of Mean Component Costs Method
  • 2.8Future Trends in Project Cost Estimation
  • 2.9Innovation in Cost Estimation Techniques
  • 2.10Summary of Literature Review

Chapter THREE

RESEARCH METHODOLOGY

  • 3.1Research Methodology Overview
  • 3.2Research Design and Approach
  • 3.3Data Collection Methods
  • 3.4Sampling Techniques
  • 3.5Data Analysis Procedures
  • 3.6Validity and Reliability Measures
  • 3.7Ethical Considerations in Research
  • 3.8Limitations of the Research Methodology

Chapter FOUR

DATA PRESENTATION AND ANALYSIS

  • 4.1Analysis of Project Cost Estimation Data
  • 4.2Comparison of Estimated Costs vs. Actual Costs
  • 4.3Factors Influencing Project Cost Variance
  • 4.4Interpretation of Findings
  • 4.5Discussion on the Accuracy of Mean Component Costs Method
  • 4.6Recommendations for Improving Cost Estimation
  • 4.7Implications for Project Management
  • 4.8Future Research Directions

Chapter FIVE

SUMMARY, CONCLUSION AND RECOMMENDATIONS

  • 5.1Conclusion and Summary of Findings
  • 5.2Recap of Research Objectives
  • 5.3Key Contributions of the Study
  • 5.4Practical Applications of Research Findings
  • 5.5Suggestions for Further Research

Project Abstract

<p> </p><div>Building construction project has become an everyday issue, and this involves the spending of hard earned money by the project owner called the client. The expectation of the owner of any building project is justification of good project delivery.Analytical and approximate variance of public building total project cost, estimation by mean component costs method.This is enabled by the objectives of the project which definitely includes project cost that envelopes the cost and quality of delivery at the expected time. The major issue, is the project cost which dictates its success. Project cost variance has been affecting the speedy and successful delivery of building construction projects. The key fact in this study method was to collect and analyse public building project cost estimates containing building components, which includes preliminaries, substructure, superstructure, mechanical/electrical, external works and contingency in the bill of quantity (BOQ) from projects handled by Education Trust Fund(ETF) in the tertiary institutions located in Kaduna, Kwara, Kogi and Abuja from 2009 to 2010. The study adopted mean component cost method modeled by Skitmore and Ng (2002) to determine the projected cost variance of the Lecture Theatres and Lecture Rooms handled by the organization in various tertiary institutions in Nigeria. The analysis of the data collected was made by using standard method of analysis which employs SPSS for the project costs.Skitmore and Ng (2002) model was employed to test the variability of the project cost data. The result shows that; the building component cost data 4782.50 had closer link to the mean 4773.92(mean) for preliminaries component column in project ID 4 of Lecture Theatreandanother component data 2797.62 is also close to 2312.91(mean) for Ext.Wkscolumn in project ID 7 for the Lecture Theatre building projects butfor the Lecture Classrooms building the preliminaries column had 1531.41 and 1416.33(mean) in project ID 2 and 1611.22 and 1673..58(mean) for M/E column for project ID 5. This project therefore concludes in addition to the results of the cost variances, that the lecture theatre and classrooms projects are underestimated.Interview was also conducted on the professional estimators in building industry. Moreover significant differences exist among the components in those public buildings.The analytical calculation shows that the correct variance for an average lecture theatre project from this research was found to be 34.73%. The sample analyzed had shown that the correct variance of the class room was found to be 38. 50%. Therefore lecture theatre is observed to be a better building project than the class room building. The study recommends the need to minimize the occurrence of the overrun by thoroughly crosschecking the initial estimate and addressing other technical issues before the contract is awarded. It also recommends the employment of the mean component cost method of analysis and setting of a committee to properly scrutinize the estimate.</div><br> <br><p></p>

Project Overview

<p> </p><div>In the building construction industry, it is a formal procedure to determine the initial cost of a building project before awarding the contract. This is in order to ascertain the financial level of the client whether the project is worth undertaking. The underlyingfact is because of the instability of the market prices of material, labour and equipment which are the major tools involved in the construction.</div><div>The wave of project production cost variability in the recent time calls for a concern in the building industry. If a building project cost estimate is presented for tender and the contractor gives his quotations, with all necessary adjustment made and contract is awarded, it is not likely that the agreed contract price will still be the final project cost at completion. The final project cost is often found to be higher at completion.</div><div>There are many factors leading to the changes in the final cost. Giwa (1998) had stated that the effect of change between the initial and the final cost incurred constitute a major problem in the building industry, especially between the client and estimator. This cost differential is called cost variance in the building construction industry. Cost variance is significant for general cost planning, and can be a big problem to solve by the managers in the building industry.</div> <br><p></p>

Blazingprojects Mobile App

📚 Over 50,000 Project Materials
📱 100% Offline: No internet needed
📝 Over 98 Departments
🔍 Software coding and Machine construction
🎓 Postgraduate/Undergraduate Research works
📥 Instant Whatsapp/Email Delivery

Blazingprojects App

Related Research

Building. 3 min read

Smart Building Energy Management and Automation System with IoT Integration...

What This Project Is About A simple look at how a building can automatically use electricity, lighting, heating, and cooling more efficiently by using internet-...

BP
Blazingprojects
Read more →
Building. 3 min read

Smart Building Occupancy Prediction and Energy Optimization using IoT Sensors...

What This Project Is About A straightforward exploration of how smart sensors in a building can monitor where people are and how much energy is used, then use t...

BP
Blazingprojects
Read more →
Building. 4 min read

Smart Gated Community Building Management System (SC-BMS)...

What This Project Is About A plain-language overview of the topic and what the project investigates. The Problem It Addresses What problem or gap this project ...

BP
Blazingprojects
Read more →
Building. 4 min read

Smart Grid-Integrated Building Management System for Energy Efficiency and Occupant ...

What This Project Is About A plain-language overview of how a building management system can work together with the local electricity grid to save energy and im...

BP
Blazingprojects
Read more →
Building. 4 min read

Smart Structural Health Monitoring System for Adaptive Truss Bridges using Wireless ...

What This Project Is About A straightforward exploration of a system that monitors the health of adaptive truss bridges using wireless sensors. The project look...

BP
Blazingprojects
Read more →
Building. 4 min read

Smart Composite Reinforced Concrete for Seismic-Resistant Building Frames...

What This Project Is About A plain-language overview of the topic and what the project investigates. The Problem It Addresses What problem or gap this project ...

BP
Blazingprojects
Read more →
Building. 2 min read

Smart Concrete: Development and Evaluation of Self-Healing Concrete for Structural L...

What This Project Is About A practical exploration of smart, self-healing concrete that can repair small cracks automatically, extending the life of concrete st...

BP
Blazingprojects
Read more →
Building. 3 min read

Smart Building Energy Management System with IoT-Driven Adaptive HVAC and Lighting C...

What This Project Is About A plain-language overview of the topic and what the project investigates. The Problem It Addresses What problem or gap this project ...

BP
Blazingprojects
Read more →
Building. 2 min read

Smart Modular Housing System with Integrated Energy Harvesting and IoT-based Smart V...

What This Project Is About A clear, practical study of modular housing that can be assembled quickly, powered partly by energy captured from the environment, an...

BP
Blazingprojects
Read more →
WhatsApp Click here to chat with us