Home / Building / AN ASSESSMENT OF CONTRACTOR’S RISKS EXPOSURE WITHIN SOME STANDARD FORMS OF BUILDING CONTRACT IN NIGERIA

AN ASSESSMENT OF CONTRACTOR’S RISKS EXPOSURE WITHIN SOME STANDARD FORMS OF BUILDING CONTRACT IN NIGERIA

 

Table Of Contents


Thesis Abstract

<p> </p><p>Construction projects are subjected to several risks due to different activities involved. The activities are performed by several parties.An assessment of contractor’s risks exposure within some standard forms of building contract in nigeria .under different circumstances. Among the various stakeholders the Contractor has been identified to be the party that carries the highest number of risks. They are mostly exposed to contractual risks which occur as a function of contract provisions and clauses. This research work identified and assessed the risks which Contractors are exposed to within some Standard Forms of Contract in Nigeria. It further determined the likelihood of occurrence of the identified risks, impact on the risks on Contractors and the level of risks. Data were collected through questionnaires distributed to some Contractors around Abuja and analysed using qualitative risk analysis technique. The research identified 35 potential risk factors with 54% of the risks emanating from the Clients, 31% from the Architect, 6% from the Quantity Surveyor, 6% from the Project Managers and 3% from the government agents. It also found out that failures to write instructions regarding variations and documents which are not issued on time are the major potential risk factors with high likelihood of occurrence while the other risk factors have moderate likelihood of occurrence. Thirteen (13) potential risk factors were found to have high impact on Contractors and fifteen (15) are high degree of risk. It concluded that Contractors must understand the nature of risks, their source and the extent of exposure so as to pay attention to dealing with such risks in present and future projects. The study therefore recommended that Contractor should pay attention to risks with high likelihood of occurrence so as to reduce their impact, should protect themselves against risks by contingency, warn parties of potential delays and its implications, negotiate construction schedule with client and allow for buffer time, the contractor should ensure working with carefully prepared and coordinated drawings, establish clear line of communications for receiving and responding to instructions and collaborative effort from all the participants of the project.</p><br> <br><p></p>

Thesis Overview

<p> The construction industry is a unique and dynamic industry of the economy; in Nigeria it accounts for over 1.4% of its Gross Domestic Product and also it is a large employer of labour (Oluwakiyesi, 2011). But over the years it has been criticized for its expensive and wasteful nature, low productivity, quality problem and project delay. The reasons for all these being are as varied, diverse and complex as the products of this industry itself. The process of developing a project from initial investment appraisal to completion and into use is complex (Flanagan and Norman, 2003). It is a generally recognized fact that those within the construction industry are continually faced with a variety of situations involving many unknown, unexpected, frequently undesirable and often unpredictable factors. These uncertain situations according to Turner (1990) have made many projects to fall short of the desired objectives of cost, time, quality and satisfaction. Project Management Institute (2000) defines risk as uncertain event or condition that if it occurs has a positive or negative effect on the project objective. Bufaied (1987) also describes risk in relation to construction as a variance in the process of a construction project whose variation results in uncertainty as to the final cost, duration and quality of the project. There are many risks involved in construction projects, which could be attributed to a number of reasons; amongst them are the nature of the construction process, the complexity and time-consuming design and construction activities, the involvement of a multitude of people, from different organizations, with different skills and interests, all resulting in accumulative associated risks for the project. Hence, a great deal of effort is required to co-ordinate the wide range of activities that are undertaken (Chapman and Ward, 1997; Shen, 1999). As the size and complexity of the projects have increased, the ability to manage risks throughout the construction processes has become a central concern in the attempt to prevent unwanted consequences (Maytoren et al., 2007). <br></p>

Blazingprojects Mobile App

📚 Over 50,000 Project Materials
📱 100% Offline: No internet needed
📝 Over 98 Departments
🔍 Project Journal Publishing
🎓 Undergraduate/Postgraduate
📥 Instant Whatsapp/Email Delivery

Blazingprojects App

Related Research

Building. 2 min read

Implementation of Smart Building Energy Management System...

The project titled "Implementation of Smart Building Energy Management System" aims to address the growing need for more sustainable and efficient ene...

BP
Blazingprojects
Read more →
Building. 3 min read

Implementation of Smart Building Automation System using IoT Technology...

The project titled "Implementation of Smart Building Automation System using IoT Technology" aims to explore the integration of Internet of Things (Io...

BP
Blazingprojects
Read more →
Building. 3 min read

Development of an Energy-Efficient Smart Building System...

The project titled "Development of an Energy-Efficient Smart Building System" aims to address the growing need for sustainable and environmentally fri...

BP
Blazingprojects
Read more →
Building. 2 min read

Integration of Renewable Energy Sources in Building Design for Enhanced Sustainabili...

The project titled "Integration of Renewable Energy Sources in Building Design for Enhanced Sustainability" aims to explore the integration of renewab...

BP
Blazingprojects
Read more →
Building. 3 min read

Implementation of Green Building Technologies for Sustainable Construction Practices...

The project titled "Implementation of Green Building Technologies for Sustainable Construction Practices" focuses on the integration of environmentall...

BP
Blazingprojects
Read more →
Building. 2 min read

Design and Implementation of a Smart Energy Management System for Residential Buildi...

The project titled "Design and Implementation of a Smart Energy Management System for Residential Buildings" aims to address the growing importance of...

BP
Blazingprojects
Read more →
Building. 2 min read

Design and Construction of a Sustainable Green Building Using Recycled Materials...

The project titled "Design and Construction of a Sustainable Green Building Using Recycled Materials" aims to address the growing need for sustainable...

BP
Blazingprojects
Read more →
Building. 3 min read

Analysis and optimization of energy consumption in smart buildings....

The research project titled "Analysis and Optimization of Energy Consumption in Smart Buildings" aims to investigate and improve the energy efficiency...

BP
Blazingprojects
Read more →
Building. 4 min read

Design and Analysis of Sustainable Building Materials for High-Rise Structures...

The project titled "Design and Analysis of Sustainable Building Materials for High-Rise Structures" aims to address the increasing need for environmen...

BP
Blazingprojects
Read more →
WhatsApp Click here to chat with us